Hwy 53 Project Update 7-12 to 7-24

Hwy 53 Project Update 7-12 to 7-24

July 13, 2021 News -- KSDM-KGHS 0

Traffic impacts

A rendering of the Hwy 53 International Falls project.

Work of July 12 – 17

Memorial to 20th Street (Stage 2)

  • Manhole cover work
  • Striping
  • Detour removed and reopen to traffic July 15

15th Street to Industrial Ave. (Stage 3C)

  • Detour removed and currently open to traffic

Industrial Ave. to 10th Street (Stage 3A)

  • Begin storm sewer work on east side
  • West lane open to traffic

Hwy 11 to Border

  • Begin removals on north end July 13

Work of July 19 – 24

Access Road

  • Removals and grading from north end moving south
  • Business access from the south

Crescent Dr.

  • Entrance culvert work
  • Business access from north and south

Industrial Ave. to 10th Street (Stage 3A)

  • Continue storm sewer work east side
  • Westlane open to traffic.

Hwy 11 to Border

  • Continue removals north to south