Hwy 53 Project Update 10/06/21

Hwy 53 Project Update 10/06/21

October 6, 2021 News -- KSDM-KGHS 0
A rendering of the Hwy 53 International Falls project.

Work of October 5 – 16

Crescent Dr. (Stage 2)

  • Grading and culverts early October
  • Bituminous pavement mid October

Industrial Ave to 10th Street (Stage 3)

  • No work

10th Street to 3rd Street (Stage 4)

  • 7th St – 3rd St
    • Grading, Curb and Gutter in early October
    • Sidewalks and lighting in mid October
    • Bituminous paving in mid to late October
  • 7th St – 10th St
    • Concrete Sidewalks and Driveways
    • Bituminous paving in mid October

Hwy 53 to the Border (Stage 5)

  • Bituminous paving before Oct 15